On Moravské náměstí in Brno, right next to the Ferris wheel, stands our new ticket booth for the public ice rink. It is a contract for the City of Brno that we won in a public tender.
It was a real challenge. Windows, PIR panels, roller shutters and a special frame with a flat roof normally take at least 4–5 weeks to arrive. From winning the tender to handover we had 34 days for absolutely everything. So we visited every supplier in person and asked for the earliest possible date. They all accommodated us, also thanks to our large orders and on-time payments. The cladding was laser cut to order.
How it went
- 8 Oct 2026 we entered the tender
- 20 Oct we were told we had won
- The delivery deadline was 23 Nov 2026
- We delivered the booth on 22 Nov, a day ahead of the deadline
Structure and insulation
- Special fully welded steel frame with a flat roof
- 100 mm PIR in the walls and roof
- 150 mm PIR in the floor
- Heat transfer coefficient U = 0.22 W/m²K
- Floor: waterproof 18 mm CETRIS board and SPC vinyl
- Cassette cladding RAL 9006, laser cut
- Rainwater drainage through four pipes hidden in the corner posts
Booth equipment
- Aluminium sliding window 120 × 90 cm with a counter
- Aluminium ventilation window 120 × 90 cm
- Security entrance door 90 cm with two FAB locks
- Hörmann windows and doors with insulated double glazing
- 2× external roller shutter with electric drive and remote control
- NW2 ceiling infrared panel with thermostat
- LED light 60 × 60 cm
- The price includes the electrical inspection report
Price (incl. delivery and placement)
449,000 CZK + VAT